Starflex Energy (M) Sdn. Bhd. vs. Gema Antara Sdn. Bhd.

The plaintiff, Starflex Energy (M) Sdn. Bhd., claimed RM1,372,757.50 from the defendant, Gema Antara Sdn. Bhd., for unpaid works and materials supplied in a construction project. The defendant counterclaimed for damages due to alleged delays and defective works. The High Court of Malaya at Shah Alam ruled in favor of the plaintiff, awarding RM718,501.00 with interest and dismissing the defendant's counterclaim.

Overview

Case Number

BA-22C-41-10/2020

Case Type

Civil - Contract dispute

Court

High Court of Malaya at Shah Alam, Shah Alam, Selangor

Coram Judge

Related Proceedings

Subject Matter

contract lawconstruction disputesbreach of contract

Documents