Tang Hang Tow (trading as Tang Construction) v Fixus Construction Sdn Bhd
The Appellant, Tang Hang Tow (trading as Tang Construction), appealed against the Session Court's decision dismissing its claim for RM334,571.64 in unpaid progress claims and granting the Respondent's counterclaim for RM301,192.69 plus damages. The High Court dismissed the appeal, finding no error in the Session Court's findings regarding project delays, payment claims, termination of the Letter of Award, and rectification works.
Overview
Case Number
WA-12BC-4-04/2023
Case Type
Civil - Construction contract dispute
Court
High Court of Malaya at Kuala Lumpur, Kuala Lumpur
Coram Judge
- Nadzarin Wok NordinDelivered Judgment
Related Proceedings
High Court
WA-12BC-4-04/2023
High Court of Malaya at Kuala Lumpur
Court of Appeal
Subject Matter
construction lawcontract lawpayment claimsquantum meruit